SI Portal - PO Quantity should be 0 if new lines added

Summary:
SI Portal - PO Quantity should be 0 if new lines added

Ticket:

DCM-2432 - Getting issue details... STATUS

Detail:

  • For the SI Packing, if a line did not previously exist on the Booking, then we now set the Booked Quantity to 0


Load XUS - Accept EST events once Planned

Summary:
Load XUS - Accept EST events once Planned

Ticket:

DCM-2269 - Getting issue details... STATUS

Detail:

  • Currently, we do not accept ‘EST’ when the Shipment is ‘COB’/'Planned' but this validation has been removed.