Implementation

Pages

Table of Contents

Timelines

White Glove project software requirements started: 23rd November 2021

White Glove project software implementation phase 1 start: 24th Jan 2022

ROOM products warehouse move: 28th March 2022

ROOM go live with Smart Hub 2.0 (White Glove module) ~31st March as long as data can be loaded into the system.

Overall Dates

  1. Should it be pushed back a week based on API not being ready from ROOM?

ROOM Current Product master list load into SEKO 360 WMS

@Alon, @James Clarification of Product Master List to load into SEKO 360 WMS (@Catherine at ROOM)
@Alon, @Jeric Load into SEKO 360 WMS

Warehouse Move from Germany to Netherlands (AAV)

@Dan Physical move of stock Sat 26th March - Mon 28th March
@Dan Upload stock into SEKO 360 against ROOM product master list

White Glove Software Dependencies / Information Required

@james Work out APIs for CargoWise (Adam)
@james endpoint for CargoWise (Adam)
@james ask ROOM regarding dispatch

ROOM restart bookings

Decision to be made whether using CSV or API if ready (~31st March)

White Glove Going Live

@james @room @alon CSV upload for ROOM bookings as short term prior to API calls being ready
@Dan to send some CSVs through (ASN/TO/SO)
@ROOM api calls ready and tested for White Glove
@ROOM api calls ready and tested for SEKO 360 for inventory requests

White Glove (Smart Hub 2.0) software into production

Â