Action & Owner

Description

Team

  •  Create & Agree Project Name

PROJECT SUEZ

Mark Blair

  •  Set up call with Sergey V around microservices - potential add dedicated resource to support

Mark Blair / Alon

  •  Provide Luca with access to Angular Playground - holds everything except for base Kendo components

Adam & Steve

  •  Model Knauf fields into DOM

Adam

  •  Building Design into the Process - separate workstream? - do this in big picture

Adam & James

  •  Project Plan / Themes in Big Picture
  •  Big Picture, Miro, and Figma licences from Alon

Adam & Luca

  •  Start cataloguing required components

Alon

  •  Indigina email for Luca

Adam

  •  Get Stuart to manage the feedback / updated process

Adam

  •  Set up regular calls with various stakeholder groups
    •  Sprint Pre-Planning
    •  Sprint Retrospective & Planning
    •  Stakeholder Updates
    •  Daily Standups

Adam

  •  Agree reporting with Semyon - by story or by task type (iTrans preferred)

Objectives

  • Project Plan & Communication - Status Updates, etc

  • More information on the system requirements

  • Agreement on agile process, team operation etc

  • First steps on technical/team standup

  • Responsibilities - putting items on the backlog, refinement, definition of ready

  • Tooling - Team Gantt, JIRA, Big Picture etc

  • Clarification of interactions with other projects

  • Bounded context & microservices, break down application as much as possible

  • How to implement the design process within the overall approach

...

UI Dev - Maybe swap for backend?

Seymon -

  • how do we measure business success of project?

  • reporting on hours would be by user and task type unless we ask otherwise

  • budget - what happens when the team structure changes, and what is min/max team size?

  • sprint pre-planning - dev team & product owner to agree priority & feasibility - flag if any blockers, or technical stories are needed

Risks/Issues

Risk/Issue

Type

Mitigation

Spec not detailed enough in time

Risk

Ensure sufficient detail for development team to start prototype designs using agreed frameworks/patterns

...