Timelines

White Glove project software requirements started: 23rd November 2021

White Glove project software implementation phase 1 start: 24th Jan 2022

ROOM products warehouse move: 28th March 2022

ROOM go live with Smart Hub 2.0 (White Glove module) ~31st March as long as data can be loaded into the system.

ROOM Current Product master list load into SEKO 360 WMS

  • @Alon, @James Clarification of Product Master List to load into SEKO 360 WMS
  • @Alon Load into SEKO 360 WMS

Warehouse Move from Germany to Netherlands (AAV)

  • @Dan Physical move of stock Sat 26th March - Mon 28th March
  • @Dan Upload stock into SEKO 360 against ROOM product master list

White Glove Software Dependencies / Information Required

  • @james Work out APIs for CargoWise (Adam)
  • @james endpoint for CargoWise (Adam)

White Glove Going Live

  • @james @room @alon CSV upload for ROOM bookings as short term prior to API calls being ready
    • @Dan to send some CSVs through (ASN/TO/SO)
  • @ROOM api calls ready and tested for White Glove
  • @ROOM api calls ready and tested for SEKO 360

White Glove project software into production

  • @dev Deploy to live user story WG-253 - Getting issue details... STATUS to ensure every product SKU in the payload is a master SKU
  • @ROOM Load sales orders from SmartHub 1.0
  • @dev Reengineer existing bookings to reflect live status WG-77 - Getting issue details... STATUS