Pages
Table of Contents
Timelines
White Glove project software requirements started: 23rd November 2021
White Glove project software implementation phase 1 start: 24th Jan 2022
ROOM products warehouse move: 28th March 2022
ROOM Current Product master list load into SEKO 360 WMS
- @Alon, @James Clarification of Product Master List to load into SEKO 360 WMS
- @Alon Load into SEKO 360 WMS
Warehouse Move from Germany to Netherlands (AAV)
- @Dan Physical move of stock Sat 26th March - Mon 28th March
- @Dan Upload stock into SEKO 360 against ROOM product master list
White Glove Software Dependencies / Information Required
- @james Work out APIs for CargoWise (Adam)
White Glove Going Live
- @james @room @alon CSV upload for ROOM bookings as short term prior to API calls being ready
- @ROOM api calls ready and tested for White Glove
- @ROOM api calls ready and tested for SEKO 360