Pages
Table of Contents
Timelines
White Glove project software requirements started: 23rd November 2021
White Glove project software implementation phase 1 start: 24th Jan 2022
ROOM products warehouse move: 28th March 2022
ROOM go live with Smart Hub 2.0 (White Glove module) ~31st March as long as data can be loaded into the system.
Overall Dates
- Should it be pushed back a week based on API not being ready from ROOM?
ROOM Current Product master list load into SEKO 360 WMS
- @Alon, @James Clarification of Product Master List to load into SEKO 360 WMS (@Catherine at ROOM)
- @Alon, @Jeric Load into SEKO 360 WMS
Warehouse Move from Germany to Netherlands (AAV)
- @Dan Physical move of stock Sat 26th March - Mon 28th March
- @Dan Upload stock into SEKO 360 against ROOM product master list
White Glove Software Dependencies / Information Required
- @james Work out APIs for CargoWise (Adam)
- @james endpoint for CargoWise (Adam)
- @james ask ROOM regarding dispatch
ROOM restart bookings
- Decision to be made whether using CSV or API if ready (~31st March)
White Glove Going Live
- @james @room @alon CSV upload for ROOM bookings as short term prior to API calls being ready
- @Dan to send some CSVs through (ASN/TO/SO)
- @ROOM api calls ready and tested for White Glove
- @ROOM api calls ready and tested for SEKO 360 for inventory requests
White Glove (Smart Hub 2.0) software into production
- @dev Deploy to live user story - WG-253Getting issue details... STATUS to ensure every product SKU in the payload is a master SKU
- @ROOM Load sales orders from SmartHub 1.0 via API
- @dev Manually adjust existing bookings from Smart Hub 1.0to reflect live status - WG-77Getting issue details... STATUS
- @Dan send usernames for Seko Farnborough
- @Bart-Jan send usernames of users for AAV
- @James DCs set up on live system (AAV (NL), SYD (AUS), FAB (UK)) for client ROOM and UAT
- @James Send detail eg. address on DCs for AAV and SYD to Cristina